LOADSHADING UPDATE

The implementation of loadshedding will be escalated to Stage 6 during the night, starting at 21:00 tonight until 05:00 on Wednesday morning. Stage 6 nightly loadshedding will then be implemented at 16:00 -05:00 until further notice. Stage 4 loadshedding will be implemented at 05:00 – 16:00 daily until further notice.
Eskom will promptly communicate a further update as soon as there are any significant changes.

Seven units tripped today, of which three have returned to service. In addition, the return to service of three other units has been delayed. Unit 1 of Matla Power Station will be shut down tonight to repair a boiler tube leak.